Time Frame for mkSolaire
January, 2008
Site Work: Grading/Utility Lines
February, 2008
Factory: Insulation/MEP/Finish work
March, 2008
Site Work: House Gets Shipped and Set March 5, 2008

April, 2008
Site "Button-up" Work: Utilities tied in; finishing, decks, landscaping completed

May, 2008
House Completed on May 5, 2008