Time Frame for mkSolaire

January, 2008

Site Work: Grading/Utility Lines

Factory: Framing

February, 2008

Site Work: Foundations

Factory: Insulation/MEP/Finish work

March, 2008

Site Work: House Gets Shipped and Set March 5, 2008

April, 2008

Site "Button-up" Work: Utilities tied in; finishing, decks, landscaping completed

May, 2008

House Completed on May 5, 2008